A _______________ is developed using historical cost information that relates some software metric to the project cost ?
A. Algorithmic cost modelling
B. Expert judgement
C. Estimation by analogy
D. Parkinson’s Law
Explanation: The model uses a basic regression formula with parameters that are derived from historical project data and current as well as future project characteristics.