In a network diagram, the activity that must be completed prior to the start of anactivity is called as

Question:

In a network diagram, the activity that must be completed prior to the start of anactivity is called as

A.

Successor activity

B.

Predecessor activity

C.

Concurrent activity

D.

Dummy activity

Answer» b. Predecessor activity