With reference to project management, identify which of the following statement is NOT correct?

Question:

With reference to project management, identify which of the following statement is NOT correct?

A.

Gantt chart is a principal tool used in scheduling and also in some methods of loading.

B.

Routing is the first step in the production planning.

C.

The cost of any activity is proportional to its time of completion.

D.

The free float can be calculated by subtracting EFT from EST.

Answer» d. The free float can be calculated by subtracting EFT from EST.