A can do a piece of work in 4 hours; B and C together can do it in 3 hours, while A and C together can do it in 2 hours. How long will B alone take to do it?

Question: A can do a piece of work in 4 hours; B and C together can do it in 3 hours, while A and C together can do it in 2 hours. How long will B alone take to do it?
[A].

8 hours

[B].

10 hours

[C].

12 hours

[D].

24 hours

Answer: Option C

Explanation:

A’s 1 hour’s work = 1 ;
4
(B + C)’s 1 hour’s work = 1 ;
3
(A + C)’s 1 hour’s work = 1 .
2
(A + B + C)’s 1 hour’s work = 1 + 1 = 7 .
4 3 12
B’s 1 hour’s work = 7 1 = 1 .
12 2 12

B alone will take 12 hours to do the work.