10 women can complete a work in 7 days and 10 children take 14 days to complete the work. How many days will 5 women and 10 children take to complete the work?

Question:
10 women can complete a work in 7 days and 10 children take 14 days to complete the work. How many days will 5 women and 10 children take to complete the work?

[A].

3

[B].

5

[C].

7

[D].

Cannot be determined

Answer: Option C

Explanation:

1 woman’s 1 day’s work = 1
70
1 child’s 1 day’s work = 1
140
(5 women + 10 children)’s day’s work = 5 + 10 = 1 + 1 = 1
70 140 14 14 7

5 women and 10 children will complete the work in 7 days.