Question:
39 persons can repair a road in 12 days, working 5 hours a day. In how many days will 30 persons, working 6 hours a day, complete the work?
[A].10
13
14
15
39 persons can repair a road in 12 days, working 5 hours a day. In how many days will 30 persons, working 6 hours a day, complete the work?
[A].
[B].
[C].
[D].
Answer: Option B
Explanation:
Let the required number of days be x.
Less persons, More days (Indirect Proportion)
More working hours per day, Less days (Indirect Proportion)
Persons | 30 | : | 39 | :: 12 : x | |
Working hours/day | 6 | : | 5 |
30 x 6 x x = 39 x 5 x 12
x = | (39 x 5 x 12) |
(30 x 6) |
x = 13.