PERT is___________________?

PERT is___________________?

A. an analytic tool in concept
B. limit up of event oriented diagrams
C. used for research and development projects
D. based on three time estimates for activities linking up two events
E. all of the above

The assumption in PERT is__________________?

The assumption in PERT is__________________?

A. a project will always be behind schedule, if left uncorrected
B. cost of project will always be more than the estimated cost, if no timely corrections are taken
C. a project can be subdivided into a set of predictable, independent activities
D. activities are fixed and can’t be changed ,
E. commissioning time can be changed, if activities are behind schedule

The important file in making a PERT is__________________?

The important file in making a PERT is__________________?

A. an event can’t be accomplished until activities leading to it are completed
B. no activity from any event can be started from preceding event till it is completed
C. length of arrow has nothing to do with time
D. every activity must be completed before end point is reached
E. all of the above

Pessimistic time is___________________?

Pessimistic time is___________________?

A. the maximum time which an activity might require
B. the average time required for a job
C. the most probable time considering all conditions
D. the minimum time in which an activity can possibly be accomplished
E. the earliest finish

In a PERT chart___________________?

In a PERT chart___________________?

A. all activities should be numbered
B. only important activities should be numbered
C. only critical activities are numbered
D. only selected activities are numbered
E. no activity is numbered